[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271912":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1271912,858,2,"多选题","桩基工程检验批质量验收要求为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","主控项目必须全部符合要求",true,{"key":16,"text":17,"correct":18},"B","主控项目应有80％合格",false,{"key":20,"text":21,"correct":18},"C","一般项目全部符合要求",{"key":23,"text":24,"correct":14},"D","一般项目应有80％合格",{"key":26,"text":27,"correct":18},"E","一般项目应有90%合格","AD","桩基工程检验批质量验收要求为主控项目必须全部符合要求而一般项目应有80％合格",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]