[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271890":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1271890,858,2,"多选题","建设单位收到工程验收报告后，应由建设单位（项目）负责人组织（ ）等单位（项目）负责人进行单位（子单位）工程验收。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工",true,{"key":16,"text":17,"correct":14},"B","设计",{"key":19,"text":20,"correct":14},"C","监理",{"key":22,"text":23,"correct":24},"D","检测",false,{"key":26,"text":27,"correct":24},"E","勘察","ABC","建设单位收到工程验收报告后，应由建设单位（项目）负责人组织施工（含分包单位）、设计、监理等单位（项目）负责人进行单位（子单位）工程验收。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]