[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1271826,858,1,"单选题","某施工单位承建某建设工程项目，该项目建设工期很紧，为了保障工程建设顺利进行，建设单位向施工单位及时提供了原始基准点、基准线和标高测控点资料，施工单位应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按照建设单位提供的资料及时开始施工",false,{"key":16,"text":17,"correct":18},"B","应做好复核工作，经审核批准后，才能进行后续相关工序的施工",true,{"key":20,"text":21,"correct":14},"C","首先进行复核，然后将复核结果报设计单位",{"key":23,"text":24,"correct":14},"D","首先进行复核，然后将结果报勘察单位审核","项目开工前应编制测量控制方案，经项目技术负责人批准后实施。对相关部门提供的测量控制为应在施工准备阶段做好复核工作，经审核后进行施工测量放线，并保存测量记录。在施工过程中应对设置的测量控制点线妥善保护，不准擅自自移动，施工过程中必须认真进行施工测量复核工作，审施工单位应履行的技术工作和职责，其复核结果应报送监理工程师复验确认后，方能进行后续相关工序的施工。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]