[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271819":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1271819,858,1,"单选题","砌体工程施工有①放线、②抄平、③摆砖、④立皮数杆、⑤挂线、⑥砌砖、⑦勾缝、⑧清理，正确顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②→③→①→④→⑤→⑥→⑦→⑧",false,{"key":16,"text":17,"correct":18},"B","②→①→③→④→⑤→⑥→⑦→⑧",true,{"key":20,"text":21,"correct":14},"C","②→③→①→⑤→④→⑥→⑦→⑧",{"key":23,"text":24,"correct":14},"D","②→①→③→⑤→④→⑥→⑦→⑧","砌体工程施工的一般工序：抄平—放线—摆砖—立皮数杆—挂线—砌砖—勾缝—清理。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]