[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271789":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271789,858,1,"单选题","施工项目上需用的材料、机械设备在许多情况下是由业主提供的，并对这种情况做出了相关规定，下列不属于此相关规定的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主如何标识、控制其提供产品的质量",false,{"key":16,"text":17,"correct":14},"B","检查、检验、验证业主提供产品满足规定要求的方法",{"key":19,"text":20,"correct":21},"C","规定新技术、新材料、新结构、新设备的策划要求",true,{"key":23,"text":24,"correct":14},"D","对不合格的处理办法","施工项目上需用的材料、机械设备在许多情况下是由业主提供的。对这种情况做出如下规定：1）业主如何标识、控制其提供产品的质量。2）检查、检验、验证业主提供产品满足规定要求的方法。3）对不合格的处理办法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]