[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271766":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1271766,858,3,"判断题","隐蔽工程在隐蔽前要检查合格后验收，涉及结构安全的试块、试件以及有关资料，应按规定进行见证取样检测，涉及结构安全和使用功能的重要分部工程要进行抽样检测。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(土建质量)专业管理实务 岗位知识","建筑工程",0]