[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1271722,858,1,"单选题","墙体节能工程验收检验批的划分也可根据与施工流程相一致且方便施工与验收的原则，由（ ）与监理（建设）单位共同商定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装单位",false,{"key":16,"text":17,"correct":18},"B","施工单位",true,{"key":20,"text":21,"correct":14},"C","检测单位",{"key":23,"text":24,"correct":14},"D","设计单位","检验批的划分也可根据与施工流程相一致且方便施工与验收的原则，由施工单位与监理（建设）单位共同商定。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]