[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1271682,858,1,"单选题","某工程在混凝土施工过程中，由于称重设备发生故障，导致工人向混凝土中掺入超量聚羧酸盐系高效减水剂，导致质量事故。该事故应判定为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","指导责任事故",false,{"key":16,"text":17,"correct":14},"B","社会、经济原因引发的事故",{"key":19,"text":20,"correct":14},"C","技术原因引发的事故",{"key":22,"text":23,"correct":24},"D","管理原因引发的事故",true,"所谓工程质量事故，是指工程质量不符合规定的质量标准或设计要求。设计错误。常分为结构方案不正确，计算简图与实际受力不符，荷载取值过小，内力分析有误等，都是诱发质量事故的隐患；自然灾害；施工和管理的原因。；工程地质的原因；设备、材料及制品不合格；建筑物使用不当",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]