[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271636,858,1,"单选题","为完成建设工程施工，发生于该工程施工前和施工过程中的技术、生活、安全、环境保护等方面的费用称为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费",false,{"key":16,"text":17,"correct":14},"B","其他项目费",{"key":19,"text":20,"correct":21},"C","措施项目费",true,{"key":23,"text":24,"correct":14},"D","规费","措施项目费：是指为完成建设工程施工，发生于该工程施工前和施工过程中的技术、生活、安全、环境保护等方面的费用。内容包括：安全文明施工费、夜间施工增加费、二次搬运费、冬雨季施工增加费、已完成工程及设备保护费、工程定位复测费、特殊地区施工增加费、大型机械设备进出场及安拆费、脚手架工程费。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]