[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1271623,858,1,"单选题","关于模板拆除施工，说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","非承重模板.只要混凝土强度能保证其表面及棱角不因拆除模板而受损时.即可进行拆除",false,{"key":16,"text":17,"correct":14},"B","拆模之前必须要办理拆模申请手续",{"key":19,"text":20,"correct":14},"C","模板拆除的顺序和方法.无具体要求时.可按先支的后拆.后支的先拆.先拆非承重的模板.后拆承重的模板及支架进行",{"key":22,"text":23,"correct":24},"D","承重模板.应在试块强度达到规定要求时.方可进行拆除",true,"保证模板拆除施工安全的基本要求中提到：（1）不承重的侧模板，只要混凝土强度能保证其表面及棱角不因拆除模板而受损时，即可进行拆除。（2）承重模板，应在与结构同条件养护的试块强度达到规定要求时，方可进行拆除。（3）拆模之前必须要办理拆模申请手续，在同条件养护试块强度记录达到规定要求时，技术负责人方可批准拆模。（4）各类模板拆除的顺序和方法，应根据模板设计的要求进行。如果模板设计无具体要求时，可按先支的后拆，后支的先拆，先拆非承重的模板，后拆承重的模板及支架。D项说法错误。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]