[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271556,858,1,"单选题","项目职业健康安全技术措施计划应由（ ）主持编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理部的技术负责人",false,{"key":16,"text":17,"correct":14},"B","项目经理部的安全工程师",{"key":19,"text":20,"correct":21},"C","项目经理",true,{"key":23,"text":24,"correct":14},"D","项目专职安全管理员","项目经理对项目的质量、安全负全面领导责任，因此项目职业健康安全技术措施计划应由项目经理主持编制。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]