[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271551,858,1,"单选题","建筑围护结构施工完成后，应对围护结构的外墙节能构造和严寒、寒冷、夏热冬冷地区外墙节能构造的现场实体检验，其抽样数量可以在合同中约定，但合同中约定的抽样数量不应低于《建筑节能工程施工质量验收规范》GB50411的要求。当无合同约定时应按照下列规定抽样：每个单位工程的外墙至少抽查（ ）处，每处一个检查点。当一个单位工程外墙有2种以上节能保温做法时，每种节能做法的外墙应抽查不少于3处。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","5","当无合同约定时应按照下列规定抽样：每个单位工程的外墙至少抽查3处，每处一个检查点。当一个单位工程外墙有2种以上节能保温做法时，每种节能做法的外墙应抽查不少于3处；",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]