[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1271497,858,1,"单选题","下列哪项属于条形基础浇筑的施工技术（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","根据基础深度宜分段分层连续浇筑混凝土.一般不留施工缝.各段层间应相互衔接.每段间浇筑长度控制在2000-3000mm距离.做到逐段逐层呈阶梯形向前推进.",true,{"key":16,"text":17,"correct":18},"B","一般应分层浇筑.并保证上下层之间不留施工缝.每层混凝土的厚度为200一300mm.每层浇筑顺序应从低开始.沿长边方向自一端向另一端浇筑.也可采取中间向两端或两端向中间浇筑的顺序.",false,{"key":20,"text":21,"correct":18},"C","大体积混凝土浇筑时.为保证结构的整体性和施工的连续性.采用分层浇筑时应保证在下层混凝土初凝前将上层混凝土浇筑完毕.浇筑方案根据整体性要求.结构大小.钢筋疏密及混凝土供应等情况，可以选择全面分层、分段分层、斜面分层等方式之一.",{"key":23,"text":24,"correct":18},"D","台阶式基础施工，可按台阶分层一次浇筑完毕（预制柱的高杯口基础的高台部分应另行分层），不允许留设施工缝.每层混凝土要一次灌足，顺序是先边角后中间，务使混凝土充满模板.","B项属于设备基础浇筑的内容；c项属于大体积混凝土浇筑的内容；D项属于单独基础浇筑的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]