[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1271494,858,1,"单选题","不属于混凝土浇筑前应先检查验收的工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隐蔽工程验收和技术复合",false,{"key":16,"text":17,"correct":14},"B","对操作人员进行技术交底",{"key":19,"text":20,"correct":14},"C","填报浇筑申请.并经监理工程师签认",{"key":22,"text":23,"correct":24},"D","报请建设单位批准",true,"混凝土浇筑前应先检查验收的工作有：（1）隐蔽工程验收和技术复合；（2）对操作人员进行技术交底；（3）根据施工方案中的技术要求，检查并确认施工现场具备实施条件，（4）填报浇筑申请，并经监理工程师签认。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]