[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271443,858,1,"单选题","一般情况下，签订成本加酬金合同不利于工程的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度控制",false,{"key":16,"text":17,"correct":14},"B","质量控制",{"key":19,"text":20,"correct":21},"C","成本控制",true,{"key":23,"text":24,"correct":14},"D","安全控制","成本加酬金合同，工程最终合同价格按承包商的实际成本加一定比例的酬金计算。在合同签订时不能确定一个具体的合同价格，只能确定酬金的比例。在这类合同中，承包商不承担任何风险，而业主承担了全部工作量和价格风险，所以承包商在工程中没有成本控制的积极性，常常不仅不愿意压缩成本，相反期望提高成本以提高其工程经济效益，这类合同的使用应受到严格限制。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]