[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271425":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271425,858,1,"单选题","当计算工期不能满足合同要求时，应首先压缩（ ）的持续时间。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","持续时间最长的工作",false,{"key":16,"text":17,"correct":14},"B","总时差最长的工作",{"key":19,"text":20,"correct":21},"C","关键工作",true,{"key":23,"text":24,"correct":14},"D","非关键工作","工期优化也称时间优化，其目的是当网络计划计算工期不能满足要求工期时，通过不断压缩关键线路上的关键工作的持续时间等措施，达到缩短工期，满足要求的目的。选择优化对象应考虑下列因素：（1）缩短持续时间对质量和安全影响不大的工作；（2）有备用资源的工作；（3）缩短持续时间所需增加的资源、费用最少的工作。故本题答案为“C”。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]