[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1271416,858,1,"单选题","成本核算的方法除了“制造成本法”外，还有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实际成本法",false,{"key":16,"text":17,"correct":14},"B","综合成本法",{"key":19,"text":20,"correct":14},"C","期间成本法",{"key":22,"text":23,"correct":24},"D","完全成本法",true,"此题有一定专业性，但此题应该不难，主要考核项目成本核算方法的知识点。施工项目成本核算的方法主要有两种：制造成本法和完全成本法。故本题的正确项为“D.完全成本法”。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]