[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1271400,858,1,"单选题","泥浆护壁钻孔灌柱桩施工工艺流程中，“第二次清孔”的下一道工序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","下钢筋笼",false,{"key":16,"text":17,"correct":14},"B","下钢导管",{"key":19,"text":20,"correct":14},"C","质量验收",{"key":22,"text":23,"correct":24},"D","浇筑水下混凝土",true,"在泥浆护壁条件下钻机钻孔完成后，应进行清除孔底沉渣工作，为第一次清孔。第一次清孔完成后检查孔底沉渣厚度是否满足设计和规范要求，进行桩孔质量验收。在下钢筋笼和钢导管时可能会碰撞孔壁，造成土颗粒脱落。因此，在浇筑混凝土前，还需要进行第二次清孔，以保证孔底沉渣厚度仍能满足设计和规范要求。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]