[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1271377,858,1,"单选题","施工组织设计应由（ ）主持编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",true,{"key":16,"text":17,"correct":18},"B","项目总工程师",false,{"key":20,"text":21,"correct":18},"C","公司项目管理部门",{"key":23,"text":24,"correct":18},"D","公司总工程师","此题比较简单，应该不难。主要考核项目施工组织的编制和审批相关规定。《建筑施工组织设计规范》GB\u002FT50502-2009第3．o．5条规定，施工组织设计应由项目负责人主持编制，可根据需要分阶段编制和审批。项目负责人，即项目经理。尽管实际项目管理中，相当一部分项目的施工组织设计为项目总工程师（技术负责人）主持编制，其实这是错误做法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]