[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1271217,858,1,"单选题","楼地面工程整体面层施工后，养护时间不应少于（ ）d抗压强度应达到5MPa后方准上人行走抗压强度应达到设计要求后，方可正常使用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","28","整体面层施工后，养护时间不应少于7d；抗压强度应达到5MPa后方准上人行走；抗压强度应达到设计要求后，方可正常使用。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]