[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1271212,858,1,"单选题","踢脚线与柱、墙面应紧密结合，踢脚线高度及出柱、墙厚度应符合设计要求且均匀一致。当出现空鼓时，局部空鼓长度不应大于（ ）mm，且每自然间或标准间不应多于2处。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","200",false,{"key":16,"text":17,"correct":18},"B","300",true,{"key":20,"text":21,"correct":14},"C","400",{"key":23,"text":24,"correct":14},"D","500","踢脚线与柱、墙面应紧密结合，踢脚线高度及出柱、墙厚度应符合设计要求且均匀一致。当出现空鼓时，局部空鼓长度不应大于300mm，且每自然间或标准间不应多于2处。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]