[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1271200,858,1,"单选题","建筑地面工程的分项工程施工质量检验的主控项目，应达到本规范规定的质量标准，认定为合格一般项目80％以上的检查点（处）符合本规范规定的质量要求，其他检查点（处）不得有明显影响使用，且最大偏差值不超过允许偏差值的（ ）%为合格。凡达不到质量标准时，应按现行国家标准《建筑工程施工质量验收统一标准》GB50300的规定处理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":21},"C","50",true,{"key":23,"text":24,"correct":14},"D","80","最大偏差值不超过允许偏差值的50%。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]