[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1271197,858,1,"单选题","屋面工程中找平层宜采用水泥砂浆或细石混凝土找平层的抹平工序应在（ ）完成，压光工序应在终凝前完成，终凝后应进行养护。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初凝前",true,{"key":16,"text":17,"correct":18},"B","终凝前",false,{"key":20,"text":21,"correct":18},"C","初凝后",{"key":23,"text":24,"correct":18},"D","终凝后","屋面工程找平层宜采用水泥砂浆或细石混凝土；找平层的抹平工序应在初凝前完成，压光工序应在终凝前完成，终凝后应进行养护。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]