[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271023":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1271023,858,3,"判断题","为防治混凝土结构构件出现所谓的“冷缝”，规范要求，混凝土运输、浇筑及间歇的全部时间不应超过混凝土的终凝时间。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"为防治混凝土结构构件出现所谓的“冷缝”，规范要求，混凝土运输、浇筑及间歇的全部时间不应超过混凝土的初凝时间。",{"id":6,"name":21,"category":22,"favorite":23},"(土建质量)专业管理实务 岗位知识","建筑工程",0]