[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270934":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1270934,858,3,"判断题","地下防水工程经建设（监理）单位检查后，可进行下道工序施工。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"地下防水工程的施工，施工单位应建立各道工序的自检、交接检和专职人员检查的制度，并有完整的检查记录；工程隐蔽前，应由施工单位通知有关单位进行验收，并形成隐蔽工程验收记录；未经监理单位或建设单位代表对上道工序的检查确认，不得进行下道工序的施工",{"id":6,"name":21,"category":22,"favorite":23},"(土建质量)专业管理实务 岗位知识","建筑工程",0]