[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1270925,858,1,"单选题","地下防水工程中，注浆过程的控制根据工程地质、注浆目的等控制（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","注浆压力",false,{"key":16,"text":17,"correct":14},"B","注浆量",{"key":19,"text":20,"correct":14},"C","注浆速率",{"key":22,"text":23,"correct":24},"D","A+B",true,"根据《地下防水工程质量验收规范》规定，地下防水工程中，注浆过程的控制根据工程地质、注浆目的等控制注浆压力和注浆量",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]