[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1270900,858,1,"单选题","混凝土预制桩的混凝土强度达（ ）的设计强度方可起吊。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","70％",true,{"key":16,"text":17,"correct":18},"B","75％",false,{"key":20,"text":21,"correct":18},"C","85％",{"key":23,"text":24,"correct":18},"D","100%","钢筋混凝土预制桩应达到设计强度的70%才可起吊；达100%设计强度才能运输和打桩。若提前吊运，必须采取措施并经过验算合格方可进行。桩在起吊搬运时，必须做到平稳，避免冲击和振动，吊点应同时受力，且吊点位置应符合设计规定。如无吊环，设计又未作规定时，绑扎点的数量及位置按桩长而定，应符合起吊弯矩最小的原则。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]