[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1270863,858,1,"单选题","预制桩桩位垂直于基础梁中心线的允许偏差为（ ）mm。注：H为施工现场地面标高与桩顶设计标高的距离。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100+0.1H",false,{"key":16,"text":17,"correct":14},"B","150+0.1H",{"key":19,"text":20,"correct":21},"C","100+0.01H",true,{"key":23,"text":24,"correct":14},"D","150+0.01H","桩位平面布置偏差：一、有基础梁的中心线1000.01Hmm，沿基础梁的中心线为150＋0.01Hmm。二、桩数为1~3根桩基中的桩允许偏差100mm；桩数为4~16根桩基中的桩允许偏差1\u002F3桩径或1\u002F3桩长；桩数大于16根桩基中的桩：（1）最外边的桩允许偏差1\u002F3桩径或1\u002F3桩长，（2）中间桩允许偏差1\u002F2桩径或1\u002F2桩长。4、保证桩的贯入度，最后10锤不超过30mm。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]