[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1270858,858,1,"单选题","后浇带应在其两侧混凝土龄期达到（ ）d后再施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":21},"C","40",true,{"key":23,"text":24,"correct":14},"D","56","3）后浇带的防水施工应符合下列规定:（1）后浇带应在其两侧混凝土龄期达到40d后再施工。（2）后浇带的接缝处理符合，上述有关施工缝的防水施工规定。（3）后浇带应用补偿收缩混凝士，其强度等级不得低于两侧混凝土（4）后浇带混凝土养护时间不得少于28d。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]