[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1270852,858,1,"单选题","采用硫黄胶泥接桩，应每（ ）kg做一组试件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50",false,{"key":16,"text":17,"correct":18},"B","100",true,{"key":20,"text":21,"correct":14},"C","200",{"key":23,"text":24,"correct":14},"D","500","静力压桩施工前应对成品桩做外观及强度检验，接桩用焊条或半成品硫磺胶泥应有产品合格证书，或送有关部门检验，压桩用压力表、锚杆规格及质量也应进行检查。硫磺胶泥半成品应每100kg做一组试件（3件）",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]