[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1270850,858,1,"单选题","混凝土预制桩采用电焊接头时，电焊结束后停歇时间应大于（ ）min。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","混凝土预制桩采用电焊接头时，电焊结束后停歇时间应大于1min，上下节平面偏差小于10mm",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]