[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1270837,858,1,"单选题","重要工程的预应力管桩应对电焊接头做（ ）％的焊缝探伤检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","10",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","100","桩在现场预制时，应对原材料、钢筋骨架、混凝土强度进行检查；采用工厂生产的成品桩时，桩进场后应进行外观及尺寸检查。施工中应对桩体垂直度、沉桩情况、桩顶完整状况、接桩质量等进行检查，对电焊接桩，重要工程应做10%的焊缝探伤检查。施工结束后，应对承载力及桩体质量做检验。对长桩或总锤击数超过500击的锤击桩，应符合桩体强度及28d龄期的两项条件才能锤击。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]