[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1270741,858,1,"单选题","以下不是工程竣工验收的要求的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","完成工程设计和合同约定的各项内容",false,{"key":16,"text":17,"correct":14},"B","建设单位已按合同约定支付工程款",{"key":19,"text":20,"correct":21},"C","有部分技术档案和施工管理资料",true,{"key":23,"text":24,"correct":14},"D","有施工单位签署的工程质量保修书","有完整的技术档案和施工管理资料才能进行工程竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]