[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1270707,858,1,"单选题","抹灰施工过程主要有①做灰饼、②基层处理洒水湿润、③阴阳角找方、④冲筋、⑤底、中层找平抹灰、⑥面层抹灰压光，正确顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②→①→④→③→⑤→⑥",true,{"key":16,"text":17,"correct":18},"B","①→②→③→④→⑤→⑥",false,{"key":20,"text":21,"correct":18},"C","①→②→④→③→⑤→⑥",{"key":23,"text":24,"correct":18},"D","②→①→③→④→⑤→⑥","抹灰施工的一般工序：基层处理洒水湿润—做灰饼、冲筋、阴阳角找方—底、中层找平抹灰—面层抹灰压光。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)专业管理实务 岗位知识","建筑工程",0]