[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270525":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270525,857,2,"多选题","施工项目成本分析的基本方法包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","比较法",true,{"key":16,"text":17,"correct":14},"B","比率法",{"key":19,"text":20,"correct":14},"C","因素分析法",{"key":22,"text":23,"correct":24},"D","横道图法",false,{"key":26,"text":27,"correct":14},"E","差额计算法","ABCE","施工项目成本分析的基本方法包括比较法、.比率法、因素分析法、差额计算法。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]