[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270517":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270517,857,2,"多选题","在特殊过程中施工质量控制点的设置方法（种类）有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","以质量特性值为对象来设置",true,{"key":16,"text":17,"correct":14},"B","以工序为对象来设置",{"key":19,"text":20,"correct":14},"C","以设备为对象来设置",{"key":22,"text":23,"correct":14},"D","以管理工作为对象来设置",{"key":25,"text":26,"correct":27},"E","以项目的复杂程度为对象来设置",false,"ABCD","特殊过程中施工质量控制点的设置方法包括：以质量特性值为对象来设置、以工序为对象来设置、以设备为对象来设置、以管理工作为对象来设置等。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]