[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270508":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270508,857,2,"多选题","某施工企业承担了某项施工任务，为保证项目目标的实现，项目经理做了以下各项工作，其中属于项目目标事前控制的内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","收集项目目标的实际值",false,{"key":16,"text":17,"correct":14},"B","定期进行项目目标的计划值与实际值比较",{"key":19,"text":20,"correct":21},"C","事前分析可能导致目标偏离的各种影响因素",true,{"key":23,"text":24,"correct":21},"D","针对影响项目目标的各种因素采取预防措施",{"key":26,"text":27,"correct":14},"E","当发现目标偏离时，采取纠偏措施进行纠偏","CD","目标事前控制包括事前分析可能导致目标偏离的各种影响因素；针对影响项目目标的各种因素采取预防措施。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]