[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270496":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270496,857,2,"多选题","将收集的资料整理和统计成与计划进度具有可比性的数据后，用实际进度与计划进度的比较方法进行比较分析。通常采用的比较方法有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":14},"B","S型曲线比较法",{"key":19,"text":20,"correct":14},"C","“香蕉”型曲线比较法",{"key":22,"text":23,"correct":24},"D","网络计划比较法",false,{"key":26,"text":27,"correct":14},"E","前锋线比较法","ABCE","通常采用的比较方法包括：横道图比较法、S型曲线比较法、“香蕉”型曲线比较法、前锋线比较法。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]