[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270492":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270492,857,2,"多选题","施工成本控制的依据包括以下内容（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程承包合同",true,{"key":16,"text":17,"correct":18},"B","施工组织设计、分包合同文本",false,{"key":20,"text":21,"correct":14},"C","进度报告",{"key":23,"text":24,"correct":14},"D","施工成本计划",{"key":26,"text":27,"correct":14},"E","工程变更","ACDE","施工成本控制的依据包括：工程承包合同、进度报告、施工成本计划、工程变更。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]