[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270489":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270489,857,2,"多选题","进度计划的调整方法中，“在实施进度计划分析基础上，确定调整原计划方法主要有以下几种：（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改变某些工作的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","改变某些设施的逻辑关系",false,{"key":20,"text":21,"correct":14},"C","改变某些工作的持续时间",{"key":23,"text":24,"correct":18},"D","改变某些节点的持续时间",{"key":26,"text":27,"correct":18},"E","改变某些工作的工艺关系","AC","确定调整原计划方法主要包括：改变某些工作的逻辑关系、改变某些工作的持续时间。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]