[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270487":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270487,857,2,"多选题","下列属于进度纠偏的管理措施的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","调整进度管理的方法和手段",true,{"key":16,"text":17,"correct":14},"B","强化合同管理",{"key":19,"text":20,"correct":21},"C","改变施工方法",false,{"key":23,"text":24,"correct":21},"D","改变施工机具",{"key":26,"text":27,"correct":21},"E","及时解决工程款支付","AB","管理措施（包括合同措施）分析由于管理的原因而影响项目目标实现的问题，并采取相应的措施，如调整进度管理的方法和手段，改变施工管理和强化合同管理等。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]