[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270485":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270485,857,2,"多选题","施工项目成本核算所提供的各种成本信息是（ ）等各个环节的依据。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","成本预测",true,{"key":16,"text":17,"correct":14},"B","成本计划",{"key":19,"text":20,"correct":14},"C","成本控制",{"key":22,"text":23,"correct":14},"D","成本分析和成本考核",{"key":25,"text":26,"correct":27},"E","成本节约",false,"ABCD","施工项目成本核算所提供的各种成本信息是成本预测、成本计划、成本控制、成本分析和成本考核等各个环节的依据。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]