[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270484":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270484,857,2,"多选题","施工准备阶段现场准备的安全技术措施包括（ ）的内容。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按施工总平面图要求做好现场施工准备",true,{"key":16,"text":17,"correct":14},"B","电气线路，配电设备符合安全要求，有安全用电防护措施",{"key":19,"text":20,"correct":14},"C","场内道路畅通，设交通标志，危险地带设危险信号及禁止通行标志",{"key":22,"text":23,"correct":24},"D","保证特殊工种使用工具、器械质量合格，技术性能良好",false,{"key":26,"text":27,"correct":14},"E","现场设消火栓，有足够的有效的灭火器材、设施","ABCE","施工准备阶段现场准备的安全技术措施包括：按施工总平面图要求做好现场施工准备；电气线路，配电设备符合安全要求，有安全用电防护措施；场内道路畅通，设交通标志，危险地带设危险信号及禁止通行标志；现场设消火栓，有足够的有效的灭火器材、设施。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]