[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270466":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270466,857,2,"多选题","关于施工缝的留设与处理的说法中，正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工缝宜留在结构受剪力较小且便于施工的部位",true,{"key":16,"text":17,"correct":14},"B","柱应留水平缝，梁、板应留垂直缝",{"key":19,"text":20,"correct":14},"C","在施工缝处继续浇筑混凝土时，应待浇筑的混凝土抗压强度不小于1.2MPa方可进行，以抵抗继续浇筑混凝土的扰动",{"key":22,"text":23,"correct":24},"D","对施工缝进行处理时，需满铺一层厚20～50mm的水泥浆或与混凝土同水灰比的水泥沙浆，方可继续浇筑混凝土",false,{"key":26,"text":27,"correct":14},"E","在施工缝处继续浇筑混凝土时，应将混凝土表面凿毛、清洗、清楚水泥浆膜和松动石子或软弱的混凝土层","ABCE","留置施工缝的位置应事先确定，施工缝应留在结构受剪力较小且便于施工的部位。柱应留水平缝，梁、板和墙应留垂直缝。施工缝的处理：在施工缝处继续浇筑混凝土时，应待浇筑的混凝土抗压强度不小于1.2MPa方可进行，以抵抗继续浇筑混凝土的扰动。而且应对施工缝进行处理。一般是将混凝土表面凿毛、清洗、清楚水泥浆膜和松动石子或软弱的混凝土层，再满铺一层厚10～15mm的水泥浆或与混凝土同水灰比的水泥沙浆，方可继续浇筑混凝土。施工缝处混凝土应细致捣实，是新旧混凝土紧密结合。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]