[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1270458":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1270458,857,2,"多选题","模板拆除的一般顺序是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先支的先拆",false,{"key":16,"text":17,"correct":18},"B","先支的后拆",true,{"key":20,"text":21,"correct":18},"C","后支的先拆",{"key":23,"text":24,"correct":14},"D","后支的后拆",{"key":26,"text":27,"correct":14},"E","先拆板模、后拆柱模","BC","模板拆除的一般顺序是先支的后拆，后支的先拆，先非承重部位后承重部位，自上而下",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)基础知识","建筑工程",0]