[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269869,857,1,"单选题","实行项目经理责任制，落实施工成本管理的组织机构和人员，明确各级施工成本管理人员的任务和职能分工、权利和责任，编制本阶段施工成本控制工作和详细的工作流程图等，这是属于施工项目成本措施的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","实行项目经理责任制，落实施工成本管理的组织机构和人员，明确各级施工成本管理人员的任务和职能分工、权利和责任，编制本阶段施工成本控制工作和详细的工作流程图等属于成本措施组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]