[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1269854,857,1,"单选题","以货币形式编制施工项目在计划期内的生产费用、成本水平、成本降低率以及为降低成本所采取的主要措施和规划的书面方案，称之为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工成本预测",false,{"key":16,"text":17,"correct":14},"B","施工成本控制",{"key":19,"text":20,"correct":14},"C","施工成本分析",{"key":22,"text":23,"correct":24},"D","施工成本计划",true,"施工成本计划指以货币形式编制施工项目在计划期内的生产费用、成本水平、成本降低率以及为降低成本所采取的主要措施和规划的书面方案。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]