[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269826":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1269826,857,3,"判断题","当进度发生偏差时，可通过改变某些工作的逻辑关系或改变某些工作的持续时间来进行纠偏。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"当进度发生偏差时，可通过改变某些工作的逻辑关系或改变某些工作的持续时间来进行纠偏。",{"id":6,"name":21,"category":22,"favorite":23},"(土建质量)基础知识","建筑工程",0]