[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269803":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1269803,857,3,"判断题","进度控制的组织措施不包括建立进度控制小组，将进度控制任务落实到个人。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"进度控制的组织措施包括建立进度控制小组，将进度控制任务落实到个人，建立进度报告制度和进度信息沟通网络，建立进度会议协调制度等。",{"id":6,"name":21,"category":22,"favorite":23},"(土建质量)基础知识","建筑工程",0]