[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1269782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1269782,857,1,"单选题","若工作的进度偏差大于该工作的（ ），说明此偏差对后续工作产生影响，应根据后续工作允许的影响程度来确定如何调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差",true,{"key":16,"text":17,"correct":18},"B","相关时差",false,{"key":20,"text":21,"correct":18},"C","相对时差",{"key":23,"text":24,"correct":18},"D","总时差","工作的进度偏差大于该工作的自由时差，说明此偏差对后续工作产生影响，应根据后续工作允许的影响程度来确定如何调整。",{"id":6,"name":27,"category":28,"favorite":29},"(土建质量)基础知识","建筑工程",0]